ROTEC, JSC together with the Ural Turbine Works (UTW), a part of ROTEC Holding, performs works on investment and construction contracts – EPC.
Under EPC-contracts the following works are performed:
Engineering — survey, design and coordination works
Procurement – materials and equipment supply
Construction – construction, assembly and commissioning works
In March 2015, ROTEC Holding finished the implementation of the export project – construction of turbine-type generator No. 7 with a capacity of 123 MW at the Ulan Bator TPP-4. The project had significant social and economic importance. It was the largest energy construction in Mongolia over the past twenty years. Commissioning a new turbine-type generator provided for a 13% increase in the capacity of the country’s power system and met the growing needs for energy resources.
ROTEC has considerable experience in engineering and construction of energy and infrastructure facilities. Scope of power capacities created or reconstructed: 2.7 Gigawatts.
Project | Customer | Implementation time frame |
---|---|---|
Construction of Akademicheskaya TPP |
Volga TGC |
2014 – 2016 |
Reconstruction of Nizhneturinskaya GRES (State District Power Plant) using combined cycle unit – 460 MW |
Volga TGC | 2013 – 2016 |
General contract + design:
|
TGC-16 | 2013 – 2016 |
TPP-4 expansion, Ulan-Bator, Mongolia using turbine-type generator T120/130-130-8MO |
Dulany IV Tsahialganstants HC | 2013 – 2015 |
Reconstruction of Izhevskaya TPP-1 using combined cycle unit – 230 MW |
TGC-5 | 2012 – 2014 |
Reconstruction of Vladimirskaya TPP-2 using combined cycle unit – 230 MW |
TGC-6 | 2011 – 2014 |
Reconstruction of Kirovskaya TPP-3 using combined cycle unit – 220 MW |
TGC-5 | 2012 – 2014 |
Reconstruction of Novogorkovskaya TPP using combined cycle unit – 330 MW |
TGC-6 | 2011 – 2014 |
Permskaya TPP-9 expansion using combined cycle unit – 165 MW |
TGC-9 | 2011 – 2014 |
Retrofitting of Novokuibyshevskaya TPP using combined cycle unit – 240 MW |
Volga TGC | 2011 – 2013 |
Project | Customer | Implementation time frame |
---|---|---|
Installation of 10 mini-power plants in the Primorsky region for the needs of the ANO Centr Amursky Tigr | ANO Centr Amursky Tigr | 2017 – 2018 |
General contract + design:
|
Solikamskbumprom | 2016 – 2018 |
General contract + design:
|
EuroChem-NorthWest | 2016 – 2018 |
General contract + design:
|
Zultcer Hemteh | 2016 – 2018 |
General contract:
|
MU construction project owner, Ulan-Ude | 2017 – 2020 |
Capital construction Kekura Substation PS 110/6 kV |
Base metals | 2017 – 2018 |
Construction of substation 110/6 kV and ETL Razrez Arshanovsky 110 kV |
Razrez Arshanovsky | 2017 – 2018 |
Reconstruction of power unit st. No. 9 TPP-22 with the replacement of turbine T-250/300 |
Gazprom energoholding | 2015 – 2019 |
Reconstruction of Minsk TPP-3 with the retiring capacities replacement.
|
Minskenergo | 2017 – 2018 |